From: Elodie Plan Date: March 10, 2009 technical Source: mail-archive.com
Hi Ethan, You can replace your initial values by your final estimates and set MAXEVAL to 0 (and rerun, but this will be shorter). Best regards, Elodie Elodie L. Plan, PharmD, MSc, PhDstudent ******************************************* Department of Pharmaceutical Biosciences, Faculty of Pharmacy, Uppsala University Box 591 - 751 24 Uppsala - SWEDEN Office +46 18 4714385 - Fax +46 18 4714003 ----------------------------------------------------
Quoted reply history
From: [email protected] [mailto:[email protected]] On Behalf Of Ethan Wu Sent: Tuesday, March 10, 2009 1:16 PM To: [email protected] Subject: [NMusers] add an item to the table after completion of a run Dear all, after long hrs and final completion, I just realized that forgetting to ask for one ETA in the output table. is there way to recove this missed eta to the output w/o going through the whole running again? thanks!
Mar 10, 2009 Ethan Wu add an item to the table after completion of a run
Mar 10, 2009 Elodie Plan RE: add an item to the table after completion of a run
Mar 12, 2009 Petra Jauslin-Stetina RE: add an item to the table after completion of a run